Wattfeld
Schematic of a data centre from the grid connection to heat recovery

Data centres for AI compute
From planning to operation

Wattfeld develops, builds and operates data centres for GPU clusters in Austria and Croatia.

01Grid

Grid connection and transformation

Data centres for AI need connection capacities in the tens of megawatts. We plan the grid connection with the network operator from the start, including our own transformation to medium voltage.

  • 110 / 20 kV
  • Network level 3–4
  • Own transformer
02Supply

Uninterruptible power supply

Battery storage and standby generators keep the facility running during grid outages. The generators can run on HVO. Rooftop solar supplements the auxiliary load.

  • Battery storage
  • Standby generators
  • Solar
03Distribution

Redundant power distribution

Every rack is supplied through two independent power paths. Switchgear and UPS systems are fully redundant, so the loss of one path does not affect operation.

  • 2N
  • Medium voltage 20 kV
  • UPS
04Cooling

Liquid cooling

For current GPU systems we use direct-to-chip liquid cooling. Dry coolers on the roof allow free cooling without chillers for most of the year.

  • Direct-to-chip
  • CDU
  • Free cooling
05White space

High power density

Our facilities are designed for rack densities of up to 130 kW. Power, cooling and floor loading are planned for that density from the start.

  • Up to 130 kW / rack
  • GPU clusters
  • Liquid-cooled
06Heat

Heat recovery

Server waste heat is raised to district heating temperature by heat pumps and fed into local heating networks. The connection is part of the design from the start, as the EU Energy Efficiency Directive provides for data centres above 1 MW.

  • Heat pump
  • District heating
  • EED Art. 26
Projects

HR1 · Croatia

HR1 is our first data centre project, under development in Croatia. Further information is available to interested parties on request.

Aerial view of a data centre roof with dry coolers and standby generators (illustrative image)
Illustrative image · Photo: Rsparks3, Wikimedia Commons (CC0)
Project
HR1
Country
Croatia
Status
Under development
Use
AI and HPC workloads
Cooling
Direct-to-chip, heat recovery
Details
On request
  1. Phase 1Site acquisition
  2. Phase 2Grid connection
  3. Phase 3Permitting
  4. Phase 4Construction
  5. Phase 5Commissioning
Partnerships

For site owners

Many industrial sites have grid connections and halls that are no longer fully used. For such sites we offer three forms of partnership.

01

Shared use

The connection and metering point stay with you. We use capacity you do not draw and contribute to the fixed cost of the connection.

02

Lease

Long-term lease of hall and yard space with our own plant room. The property remains yours.

03

Acquisition

Acquisition of part of a site or of an operating company where a site is to be divested. As an asset or share deal, depending on how the connection is held.

First contactFor an initial assessment we need the contracted connection capacity in kW and the network level.

Contact

Contact

[email protected]
Company

Wattfeld is a developer and operator of data centres. We act on our own account, not as an intermediary.

Confidentiality

Enquiries are treated confidentially. We will sign a non-disclosure agreement in advance on request.